meeting 8/15/08 GULF BRANCH
8/14/2008, Kuck, Keith wrote:
Foundation crew reports that the foundation was poured that the delivery was 90 min late but the total pour time was about 50 min. All went well and we now have a load of gravel and a load of sand in the parking lot waiting to be moved to the site Friday night. We hope to have 800 pavers for the floor in the parking lot by Friday night also. Meeting Friday will be a moving party of Pavers, Gravel and Sand.
Cheers
Keith
Foundation crew reports that the foundation was poured that the delivery was 90 min late but the total pour time was about 50 min. All went well and we now have a load of gravel and a load of sand in the parking lot waiting to be moved to the site Friday night. We hope to have 800 pavers for the floor in the parking lot by Friday night also. Meeting Friday will be a moving party of Pavers, Gravel and Sand.
Cheers
Keith